Sound Wall construction
Sent: Wednesday, May 12, 2010 2:06 PM
Subject: Sound Wall construction
Mr. Radabaugh, the contractor has informed me that they will start drilling the footings for the sound wall next week. Sorry for the short notice, but their driller became available, and they moved this work up on the schedule.
Rick Little will be coordinating our communication efforts on this, so if you would like to give input, he would be the best contact.
Thanks.,
LEMOS Charles A <== email for input
Chuck Lemos PLS
Project Manager
ODOT Area 5
Springfield
(541) 744-8080
Sent: Thursday, April 22, 2010 6:28 PM Subject: RE: Sound Walls
Jack, I have just this week received a preliminary schedule from the contractor and will try to give you a brief overview.
The $10.6M was the bid price for the complete project from the low bidder, Pacific Excavation, Inc. of Eugene. The contract has been awarded, and we have notice to proceed.
The bid price for the sound wall was $21.00 a square foot, or $1,562,400.00 total.
The contractor shows beginning site work on the sound wall on May 13, 2010, actual sound wall footing drilling starting in early June, 2010 , and the sound wall complete by mid October, 2010. Understand that this is preliminary, but the dates should not change by more than a few weeks.
The contractor intends to begin work on the project in general in early May, and finishing the project as a whole in June of 2011.
I am on vacation Friday, so if you need add ional informant, Rick Little may be able to fill in details.
You can call me next week if you want to discuss this with me.
Chuck Lemos PLS
Project Manager
ODOT Area 5
Springfield
(541) 744-8080
Just wondering if anyone knows what is being built in the field next to the new bike path, behind the Berkshire St. homes? I know they are starting preparation for the sound wall, but what is the other site they are clearing and building on?
ReplyDelete